L&T Wins Agra Metro’s Electrification Contract AGE-1 & 2
March 31, 2022 Update: UPMRC has issued contract LOA to L&T with a value of Rs. 453,29,87,622.56
March 7, 2022 Original Post: Larsen & Tourbo today emerged as the lowest bidder for the 750 V DC Third Rail electrification system of Agra Metro Phase 1 project, after Uttar Pradesh Metro Rail Corporation (UPMRC) opened financial bids.
Agra Metro’s Package AGE-1 & 2 is one of the few packages that has been tendered independently, with the rest (rolling stock, telecommunication, tracks, etc.) getting bundled along with the newly operational Kanpur Metro.
UPMRC invited bids for it in October 2021 with a Rs. 450 crore estimate and 36 month deadline – funded by the European Investment Bank (EIB) through a 450 million Euro loan.
Technical bids were opened in January to reveal 5 bidders. During evaluation, SWPL – GSC JV’s bid was found non-responsive to the tender conditions and their bid was disqualified.
Financial Bid Values:
Firm | Bid (Rs. Crore) |
Larsen & Toubro Ltd. (L&T) | 453.29 |
Linxon India Pvt. Ltd. | 491.90 |
Siemens Ltd. | 497.36 |
Alstom – KEC JV | 595.75 |
UPMRC’s Brief Scope: Design, Supply, Installation, Testing and Commissioning of Receiving cum Aux Main Substations Incl HV Cabling from Grid Substations,750 V DC 3rd Rail Traction System,33kV Cable Network, ASS, TSS and SCADA Sys for Corr-1and2 of Agra Metro Rail Project UP.
L&T’s bid of Rs. 453.29 crore was just a tad higher than UPMRC’s estimate of Rs. 450 crore, so I see a contract being awarded in the coming weeks without any negotiations or a long financial bid evaluation period.
UPMRC has stipulated a 12 month electrification completion deadline for the 3 km elevated portion of Line-1’s Priority Corridor between Taj East Gate – Fatehabad Road. That section is under construction by SAM India Builtwell (viaduct & stations) and Lisha Engineers (PAC Depot).
Back in February, Afcons Infra – SAM India JV won Line-1’s 7.93 km underground contract AGCC-02, but a LOA hasn’t been issued yet. Stay tuned!
For more updates, check out the Agra Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.
– TMRG
I am completed diploma in electrical engineering
ITI+polytechnic in electrical+ l&T training centre + DFCCIL work in kanpur
8233636119
I am Akash Pathak currently working as Service engineer on indian railway project. I am looking for oppotunity in Agra metro
Mobile+917668897099 I am Akash Pathak currently working as Service engineer on indian railway project. I am looking for oppotunity in Agra metro
I have completed diploma civil engineer in 2021
I’m Deepak. I have completed polytechnic diploma in civil branch in 2020. Now I’m working CTP-3R WDFC Project as a QA/QC laboratory technician.
If any requirement for me please contact contact me 9911730158
My self, Veerbal singh, i am civil engg.
My self, Veerbal singh, i am civil engg.
Contact no. – 7417033239
I’m electrical Engineer work 5 years experience Railway OHE, TSS, SSP, SP, Substations, Transformers, ……etc field electrical.
I’m electrical Engineer work 5 years experience Railway OHE, TSS, SSP, SP, Substations, Transformers, ……etc field electrical.
Con———- +918979848402
Email——–[email protected]
I’m electrical in diploma experience 2.5 year in Metro banglore and kanpur in electrical I’m looking for job in metro project
Maine L$T voting me training like hair Iti Ki diploma hair electrician se to
Hello
I am 23+ Years Experience as Document Controller and I wish to join L&T of Agra Metro Project.
Saqib Azmi
7895471772