HCC-URCC Launches Bangalore Metro Yellow Line’s Final Segment

Hindustan Construction Company – URC Construction (HCC – URC) JV last week celebrated launching the final segment for 19.14 km Bangalore Metro Yellow Line’s 6.34 km Package-3.

This elevated section of the 73.92 km Bangalore Metro Phase 2 project‘s Reach-5 on Marenahalli Road connects the Green Line’s RV Road Station with the upcoming HSR Layout Station on Hosur Road.

It consists of a 3.2 km double-decker viaduct between Ragigudda – Central Silkboard where 7.5m wide cantilever wings have been stitched to form a 4 lane road. The first central spine span was completed in July 2019 and launching of cantilever wings began in November 2019 – images can be viewed here.

HCC-URCC launched a total of 1197 segments for the elevated road and 2083 segments for the rail line’s viaduct using 4 launching gantry (LG) cranes and mobile cranes.

Pic via follower Chandra Mohan

HCC-URCC JV was awarded a Rs. 797.29 cr crore contract for Package 3’s civil construction (viaduct & station) in June 2017 by BMRCL with a 36 month deadline. Their scope includes 5 new stations at RV Road, Ragigudda, Jayadeva Hospital, BTM Layout and Central Silk Board.

Yellow Line’s Package 3 – view Bangalore Metro Phase 2 map & info
Pic via follower Chandra Mohan
Pic via follower Chandra Mohan

With this development, segment launching is complete for the entire 19.14 km Yellow Line connecting RV Road – Bommasandra. The final segment for Package 2 was launched by ITD Cementation on Hosur Road in April 2021.

The start of operations on Package 3 will be the last to commence which I see happening no sooner than mid-2024 at this time.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

8 Responses to "HCC-URCC Launches Bangalore Metro Yellow Line’s Final Segment"

  1. Gaurav says:

    Hey TMRG, I read that Blue star has bagged the contract for pink line tunnel ventilation system. Is that correct?

    Reply
  2. Srini says:

    How many kms of cantilever wings that are pending ?

    Reply
  3. Manjunath says:

    Well done team on achieving this milestone. This is complex bit fastest metro line construction I have seen. The double decker is really awesome.
    Can’t wait for metro to be inaugurated and I take a ride especially Jayadeva crossing which is 5 layer grade separator.

    Reply
  4. KANTARAJ TAVANE says:

    Going well so far ☺️

    Reply
  5. PG Kumar says:

    When are you completing beniganahalli railway over bridge. Pending since several months

    Reply
  6. Rajendra kumar says:

    When will Bommasandra station ready operational

    Reply

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply to KANTARAJ TAVANE Cancel reply

Your email address will not be published. Required fields are marked *