December 27, 2023 Update: DMRC has awarded DT16’s contract to Pee Pee Mandal Projects valued at Rs. 10.54 crore.

November 20, 2023 Original Post: Three firms – SC Agarwal, Pee Pee Mandal Projects and Texmaco Rail and Engineering – in October submitted bids to install track-work at Delhi Metro Violet Line (Line-6)’s existing Sarita Vihar Depot for augmenting additional maintenance facilities.

This contract (Package DT-16) of Delhi Metro’s Phase 4 project is part of the Delhi Metro Rail Corporation (DMRC)’s strategic plan to repurpose Sarita Vihar Depot for stabling and maintaining thirteen 6-coach Alstom trains of the upcoming 23.6 km Silver Line which will connect Aerocity – Tughlakabad via 16 stations.

DMRC had invited bids for this small value track-work contract in September 2023 with a Rs. 9.44 crore estimate and 540 (1.47 year) deadline.

Brief Scope: Supply, Installation, Testing and commissioning of Ballastless/Ballasted Track in Sarita Vihar depot for Augmentation of Additional Maintenance Facilities for Standard Gauge Corridor of Delhi MRTS Project of Phase-IV.

Violet Line’s Sarita Vihar Depot shot in 2015 – Photo Copyright: K Asif / Daily Mail
New layout of the Sarita Vihar Depot prepared in 2020 (view large)

All 3 bids are currently undergoing technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.

Here’s a list of DMRC’s team of contractors and consultants for Sarita Vihar and Ajronda Depot’s augmentation:

Package & ScopeContractor/Status
DDC for both depotsKirti Structural Consultants
DC-26: Sarita Vihar Depot’s Civil Remodel + Ramp to DC-07’s tunnelsYFC Projects
DC-25: Ajronda Depot’s Civil RemodelGhaziabad Mechfab
DT-11: Track-work within both depotsParas Railtech
DT-16: Track-work at Sarita Vihar Depot3 bids received (this post!)
DE-02: Electrification of both depotsSalasar Techno Engineering Pvt. Ltd.
DE-12: Electrical & Mechanical works at both depotsSudhir Power Projects

For more updates, check out the Delhi Metro section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to all updates and support the site over here.

– TMRG

written by

Global traveler who prefers mass rapid transit

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *