ITD-ITD Cem JV Lowest Bidder for Bangalore Metro’s Reach 1A
A couple days after emerging as the lowest bidder for the 7.218 km Reach 1B, the Italian-Thai Development – ITD Cementation India (ITD-ITD Cem) JV has now also turned out to be the lowest bidder for constructing the 72 km Phase 2 project’s 8.039km Reach 1A between the existing Baiyappanahalli Station and the upcoming Visvesvaraya Industrial Area Station. Along with Reach 1B, the Reach 1A section will extend the operational 18 km Purple Line further eastward by another 15.257 km to Whitefield.
The BMRCL invited bids for this package in December 2016 with an estimated cost of Rs. 670.72 crores, and the ITD-ITD Cem JV submitted the lowest bid at Rs. 689.51 crores.
Financial bid values submitted by the lowest 2 technically qualified firms:
Firm | Bid |
ITD-ITD Cem JV | Rs. 689.51 cr |
Simplex | Rs. 763.04 cr |
Note: NCC’s financial bid was not opened as they were disqualified in the technical round either due to their bid or issues stemming from their bank guarantee.
This section includes 6 new stations at Jyothipuram, KR Puram, Mahadevapura, Garudacharpalya, Doddanakundi Industrial Area, Visvesvaraya Industrial Area. The KR Puram Station will in the future also serve as an interchange for the upcoming 17 km Silkboard – KR Puram line (Phase 2A) which was just approved by the state government’s cabinet earlier this month.
The line’s exact alignment and location of stations can be viewed in this PDF released by the BMRCL in mid-December 2016.
The ‘General Information and Qualification Requirement’ section of the notice inviting tenders does not stipulate or prohibit one bidder from being awarded both Reach 1A and Reach 1B, so in the coming days, if no extraneous issues arise, then the BMRCL will go on to award the ITD-ITD Cem JV with the 72 km Phase 2 project’s 6th major civil contract:
Line | Reach | Stretch | Contractor |
Purple | 2A | Mysore Road – Pattanagere (3.945 km) |
IL&FS |
Green | 4B | Yelechenahalli – Anjanapura Twp (6.290 km) |
NCC |
Purple | 2B | Pattanagere – Challeghata (4.869 km) |
Soma |
Green | 3C | BIEC – Hessaraghata (3.031 km) |
Simplex |
Purple | 1B | Visvesvaraya Ind. Area – Whitefield (7.218 km) |
ITD-ITD Cem |
Purple | 1A | Baiyappanahalli – Visvesvaraya Ind Area (8.039 km) |
ITD-ITD Cem |
Like Reach 1B, tree cutting & demolition of the acquired properties is well underway with some land acquisition still pending as per the March newsletter. With this development, ground-work for the construction of this section is expected to begin in June 2017 and I see it opening for commercial operations no sooner than 2022.
Phase 2’s Status
Blue: Under Construction | Black: Contract Awarded | Orange: Financial Bids Opened | Purple: Bids Invited | Grey: Bids Yet to be Invited
Next in line is the 19.14 km RV Road – Bommasandra line (Reach 5) which consists of 3 civil packages – 1, 2 & 3. Stay tuned to find out who is or are the lowest bidders and eventual civil contractors for them!
April 25 2017 Update: BMRCL has awarded ITD with this section’s contract:
For more updates, check out the Bangalore section of The Metro Rail Guy!
– TMRG
TMRG, because the entire extension is being awarded to the same JV, could it mean better cooperation and coordination? Will this reduce the time required for construction and commercial operations? Thank you.
Yes, there’ll definitely be better coordination leading to time savings. And the way the ‘economies of scale’ concept works, ITD can end up making a higher profit if they plan it right.
TMRG, but won’t this be similar to putting all eggs in one basket. While the best case scenario might be better coordinated and efficient project execution, I can’t help but imagine a worst case scenario where if the company screws up, then the entire project is held back and not just a section.
Do these contracts have stipulations that assess progress periodically? penalties for insufficient progress, or inferior quality of work etc.?
Mr Pavan
Please give me a call I want discuss.with you
Regarding ITD Metro Project .
Regards
Munawar
Mob. 9845335075
Hi TMRG,
ITD-ITD Cem bidding price is lesser than the nearest competitiors by huge margin. Do you expect delay in construction due to this and finally ask for cost escalation etc., from them or they just finish fast to avoid any penalty from the bmrcl.
rgds
Madhu
Hi, I can’t comment on what they plan to do internally. Hopefully the BMRCL will keep them on a tight leash throughout the project’s course.
TMRG – this is a general question. I’m wondering why you don’t post news on the same day? I have observed there’s always a delay of 1 day.
Hi, 2 reasons:
1) Other personal/work commitments
2) My desire & goal to post/tweet only verified content. All news is verified through multiple sources before you ever see it. I’d rather be “right” than “first” to publish 🙂
pt-2 is one of the many reasons we love to visit your page TMRG.. thanks again for doing an awesome job
What do you expect him to answer to that question ? TMRG is not obligated to post on the same day nor is he a newspaper journo to earn from these blogs !
Be content with free material being supplied and if possible contribute !
Thanks.
What do you expect him to answer to that question ? TMRG is not obligated to post on the same day nor is he a newspaper journo to earn from these blogs !
Be content with free material being supplied and if possible contribute !
Thanks.
1A is Baiyappanahalli –Visvesvaraya Ind. Area and not as mentioned in the table
Nice catch! I’ve corrected it now 🙂
As a company and as a JV, how does ITD and ITD-ITD Cem measure up with other infrastructure companies like CEC, ECC, NCC, Soma and their JVs like CEC-Soma?
Hi,
Add a last column where you mention when the each project going to be commissioned.
the whole purpose of diving this into multiple packages is defeated due to same company winning both the packages , There should be rule that a company can win only 1 package in each line , other wise we have a company winning all 3/4 sections of UG and end up delaying the work
That cannot be a valid reason for delaying work because even though both packages have been won by the same JV, they still have only 27 months to finish each section individually. It cannot happen that they will work from only one end. They will have to simultaneously commence and do work on both the sections.
Ex – Hypothetically, even if the entire UG line of Phase 2 is won by a single JV, it cannot happen that they’ll use only 2/4 TBM’s for drilling, they’ll probably have to use 8-10(as TMRG said)as per the work order. I am guessing this could be the answer to your question. Thank you.
Its not only about the TBM Machines or other equipment , usually to avoid the risk of delay by one company infra projects are split into multiple packages . With 2 different companies risk would be little less . That too very important section of Whitefield metro entirely is being handed over to a single company thats my concern.
As it is BMRCL is facing huge delays with current Phase 1 . BMRCL has to ensure time bound monitoring now that the same company has got both the packages
Well then, clearly by splitting up the packages, BMRCL has had way too many missed deadlines in Phase 1. It’s beating the entire purpose of splitting, as you said. Thus, whether or not a single Jv wins the entire extension, it isn’t a reliable indicator to say that there will be a delay. More over, it could lead to shaving off time in completion as there will be better coordination.
what is the current status of underground tests for north and south corrdior any good news or postponment the opening dates.
hi tmrg
can you tell me where exactly kengeri station is going to be, have not seen any work going in that region… also is there going to be a metro station after nice road in this section
The kengeri station is coming up adjacent to Kengeri TTMC! And by the looks of the construction site, it looks to be a very big station.
sorry I belive that to be mallasandra station.
Hi TMRG, can the awarded value can be tabulated to have a grasp of value of work to be executed.Thanks
Thank you very much for providing all information and I highly appreciate your being right than first. I am curious to know if
BMRCL need any more approval before they invite bids for ORR line. And when can we expect construction to begin. Thank you
What is the expected date for completion for phase
1A is Baiyappanahalli –Visvesvaraya Ind. Area?
Hi TMRG
What is the expected date for completion for phase
1A (Baiyappanahalli –Visvesvaraya Ind. Area) ?
Thanks for your response in Advance https://media.giphy.com/media/PBM14uaJCbp72/giphy.gif