ITD Casts Mumbai Metro Line-7’s Second Crossover
ITD Cementation India Ltd. this weekend completed casting a second track crossover…
ITD Cementation India Ltd. this weekend completed casting a second track crossover…
After recommissioning Surya-1 on New Year’s Eve, workers from Larsen &…
2020 had one last surprise in store! Workers from Larsen & Toubro – Shanghai…
A few hours ago, workers from J Kumar Infraprojects erected the first 9.5m wide…
There’s something unique about each one of Mumbai Metro Line-3’s…
AECOM India today won the General Consultant (GC) service contract for civil…
Afcons Infrastructure on Tuesday began casting 28 meter long U-girders to build…
Endacom’s team on this past Friday celebrated the completion of excavation…
January 7: JSPL was issued a Letter of Award (LoA) by DMRC December 22 Original…
After recording breakthroughs in October by Surya-2 and November by Surya-1,…