Mumbai Metro Pink Line (Line-6) is a 15.18 km under construction elevated metro line connecting Swami Samarth Nagar (Lokhandwala) – JVLR – SEEPZ – Powai – Vikhroli through 13 stations.
The Mumbai Metropolitan Region Development Authority (MMRDA) is the owner of the Pink Line and Maha Mumbai Metro Operations Corporation (MMMOCL) will operate and maintain all train services.
The Detailed Project Report (DPR) for Line-6 was prepared by the Delhi Metro Rail Corporation in December 2016, and approved by the Maharashtra state government’s cabinet on 24 October 2017 with a cost of Rs. 6,672 crore.
Line-6’s three civil contracts were awarded to J Kumar Infraprojects in August 2018 (package 03) & February 2019 (package 01R1), and to MBZ-EIIL JV (package 02R) in September 2018.
Line-6’s first section is expected to open in the end of 2026 and will be connected to other metro lines, bus and suburban rail services through multiple interchanges throughout its route. The line’s official colour was revealed to the public by MMRDA on February 28, 2020 as part of a major branding exercise to establish style guidelines with help from Systra MVA Consulting.
Key Figures
Operational: 0 km | Under Construction: 15.18 km
- Estimated Cost: Rs. 6,672 crore
- Estimated Daily Ridership: 7.69 lakh/day (2031)
System Specifications
- Top Speed: 80 kmph
- Average Speed: 34 kmph
- Track Gauge: Standard Gauge – 1435 mm
- Electrification: 25 kV, 50 Hz AC OHE
- Signalling: Communication-based Train Control (CBTC)
Pink Line Route Info
Pink Line: Line-6 – Swami Samarth Nagar – Vikhroli
- Length: 15.18 km
- Type: Elevated
- Depot: Kanjurmarg (15.02 hectares)
- Number of Stations: 13
- Stations Names: Swami Samarth Nagar, Adarsh Nagar, Jogeshwari (W), JVLR, Shyam Nagar, Maha Kali Caves, SEEPZ Village, Saki Vihar, Rambaug, Powai Lake, IIT Powai, Kanjur Marg, Vikhroli (EEH)
- Note: All stations except Jogeshwari (W) and Shyam Nagar will have two levels. Concourse of these two stations will be on ground level.
Pink Line Route Map
Tentative location of Pink Line (Line-6’s) stations have been mapped out below.
Pink Line Overview Video
Pink Line Fares (Ticket Prices)
Pink Line’s fare structure, prices and rules have not been announced yet. MMRDA plans to use the latest technologies for its automatic fare collection (AFC) system to allow QR codes and phones enabled with Near Field Communication (NFC) to utilize the system.
Pink Line Tenders
Latest notices inviting tenders can be viewed on MMRDA’s website. News on these notices, their bidders, awarded tenders and contracts are covered in further detail on the news & construction page.
Pink Line’s Major Contractors
Contract | Contractor |
Line-6’s DPR Preparer | Delhi Metro Rail Corporation (DMRC) |
Line-6’s Interim Consultant | Delhi Metro Rail Corporation (DMRC) |
Line-6’s Detailed Design Consultant (DDC) | S.p.A – SMEC India Pvt. Ltd JV |
Line-6’s Independent Quality Audit Consultant | PADECO Co. Ltd. |
Package BC-01R1: Construction of IIT Powai – Vikhroli (4.771 km viaduct & 3 stations) | J Kumar Infraprojects Ltd. |
Package BC-02R: Construction of Shyam Nagar – IIT Powai (4.329 km viaduct & 5 stations) | MBZ – EIIL JV |
Package BC-03: Construction of Swami Samarth Nagar – Shyam Nagar (6.079 km viaduct & 5 stations) | J Kumar Infraprojects Ltd. |
BC-04: Architectural finishing works and erection of PEB roof at 3 stations: IIT Powai, Kanjurmarg and Vikhroli | Tender Cancelled by DMRC; Re-invited by MMRDA as CA-264 |
BC-05: Architectural finishing works and erection of PEB roof at 5 stations: Maha Kali Caves, SEEPZ Village, Saki Vihar Road, Rambaug & Powai Lake | Tender Cancelled by DMRC; Re-invited by MMRDA as CA-265 |
BC-06: Architectural finishing works and erection of PEB roof at 5 stations: Swami Samarth Nagar, Adarsh Nagar, Jogeshwari (W), JVLR & Shyam Nagar | Tender Cancelled by DMRC; Re-invited by MMRDA as CA-266 |
CT-38: 1500 MT of 90 UTS, UIC 60, 13 m, Class “A” 880 Grade Rails, IRS-T-12-2009 | Jindal Steel and Power Ltd. (JSPL) |
MT-08: Ballastless Track Fastening System | Pandrol Rahee Technologies |
MT-09R: Ballastless Track including Supply of Buffer Stop | Paras Railtech |
MT-13: Supply of 103,000 sets (41500 sets04 Anchor System and 61500 sets 02 Anchor System) Track Fastening System | Patil Rail Infrastructure Pvt. Ltd. |
CA-132: Signaling and Train Control, Telecommunication and Platform Screen Doors system contract | Tender Cancelled |
CA-130/MRS3: 108 Coach Rolling Stock contract | Tender Cancelled |
CA-208: General Consultant (GC) for Kanjurmarg Depot’s Civil Construction | Consulting Engineers Group – Korea National Railway (CEG – KNR JV) |
CA-209: Kanjurmarg Depot’s Civil Construction | Sam India Builtwell |
CA-232: 108 coach rolling stock, communication based signalling & train control, telecommunication, platform screen doors systems and depot machinery & plant including 15 years of comprehensive maintainence | Bidding Underway |
CA-233: Power Supply and Traction, E&M, Lifts and Escalators Including 15 Years of Comprehensive Maintenance | Bidding Underway |
CA-238: Automatic Fare Collection (AFC) system for Line-6 | Bidding Underway |
CA-264: Architectural finishing works at three 03 elevated stations namely IIT Powai, Kanjurmarg W, and Vikhroli EEH | Bidding Underway |
CA-265: Architectural finishing works at five 05 elevated stations namely Mahakali Caves, SEEPZ Village, Saki Vihar Road, Rambaug and Powai lake | Bidding Underway |
CA-266: Architectural finishing works at five 05 elevated stations namely Swami Samarth Nagar Adarsh Nagar, Jogeshwari W, JVLR and Shyam Nagar including two FOBs at Adarsh Nagar and JVLR Station | Bidding Underway |
Click on ‘News & Construction Updates’ below for project news, progress and updates.