Bangalore (Namma) Metro Phase 2 project with 73.921 km of new routes was approved by Karnataka’s state government’s in 2011 and by India’s Central Government in 2014.

Construction work on Phase 2’s first new section (Mysore Road – Pattanagere, Reach-2A of Purple Line) commenced in September 2015. Out of the 73.921 km length of new track, 13.885 km will be underground while the rest will be built elevated.

The project faced funding issues due to which a majority of civil construction contracts were awarded only in the first half of 2017. While the Purple Line’s extension to Challeghata & Green Line’s extension to Anjanapura Township will be ready in 2020-21, the entire phase, including a 13.885 km underground section, is expected to be ready in sections, only in 2026. Once Phase 2 is operational, the network’s total length will become 116.19 km.

Major lenders providing official development assistance (ODA) loans for this phase’s construction and procurement of systems are European Investment Bank (EIB), Asian Infrastructure Investment Bank (AIIB) and possibly Japan International Cooperation Agency (JICA).

  • BMRCL’s Current Phase 2 Deadline: 2024
  • My Completion Estimate: 2026

This phase involves the construction of 2 new lines on standard gauge tracks & the extension of both lines built in Phase 1 in all 4 directions.

Phase 2 New Lines

Official line colors were announced in November 2019

Line-3 – Yellow Line: RV Road – Bommasandra

  • Length: 19.143 km
  • Type: Elevated
  • Depot: Hebbagodi Depot (39.3 acres)
  • Number of Stations: 16
  • Station Names: Rashtreeya Vidyalaya Road (RV Road), Ragigudda, Jayadeva Hospital, BTM Layout, Central Silkboard, Bommanahalli (formerly HSR Layout), Hongasandra (formerly Oxford College), Kudlu Gate (formerly Muneshwara Nagar), Singasandra (formerly Chikkabegur), Hosa Road (formerly Basapura Road), Beratena Agrahara (formerly Hosa Road), Electronic City, Infosys Foundation Konappana Agrahara (formerly Electronic City – II), Huskur Road, Hebbagodi and Bommasandra
  • Status: Under Construction
Line-4 – Pink Line: Kalena Agaraha (formerly Gottigere) – Nagawara
  • Length: 21.386 km
  • Type: Elevated (7.501 km) and Underground (13.885 km)
  • Depot: Kothanur Depot (31.5 acres)
  • Number of Stations: 18
  • Station Names: Kalena Agrahara (formerly Gottigere), Hulimavu, IIM-Bangalore, JP Nagar 4th Phase, Jayadeva Hospital, Swagath Road Cross, Dairy Circle, Lakkasandra (foremerly Mico Industries), Langford Town, Rashtriya Military School (formerly Vellara Road), MG Road, Shivaji Nagar, Cantonment, Pottery Town, Tannery Road, Venkateshpura, Kadugundanahalli (formerly Arabic College) and Nagawara
  • Status: Under Construction

Phase 2 Line Extensions

Line-1 – Purple Line: Mysore Road – Challaghatta

  • Length: 8.814 km
  • Type: Elevated
  • New Depot: Challagatta Depot (38.9 acre; for entire line)
  • Number of Stations: 7
  • Station Names: Nayandahalli, Rajarajeshwari Nagar, Jnana Bharathi (formerly Bangalore University Cross), Pattanagere, Kengeri Bus Terminal (formerly Mailasandra), Kengeri and Challeghatta
  • Status: 7.5 km Mysore Road – Kengeri section opened on August 30, 2021. 2.1 km Kengeri – Challaghatta section opened on October 9, 2023.

Line-1 – Purple Line: Baiyyappanahalli – Whitefield

  • Length: 15.257 km
  • Type: Elevated
  • New Depot: Kadugodi Depot in Whitefield (44.8 acres; for entire line)
  • Number of Stations: 13
  • Station Names: Benniganahalli, KR Pura, Singayyanapalya, Gurudacharpalya, Hoodi, Seetharamapalya, Kundalahalli, Nallurhalli, Sri Sathya Sai Hospital, Pattandur Agrahara, Kadugodi Tree Park, Hopefarm Channasandra and Whitefield (Kadugodi)
  • Status: 13 km KR Pura – Whitefield (Kadugodi) section opened on March 26, 2023; 2.2 km Baiyyappanahalli – Benniganahalli – KR Pura section opened on October 9, 2023.

Line-2 – Green Line: Yelachenahalli (Puttenahalli) – Silk Institute (Anjanapura)

  • Length: 6.29 km
  • Type: Elevated
  • New Depot: Anjanapura Depot (8.9 acre; for entire line)
  • Number of Stations: 5
  • Station Names: Doddakallasandra (formerly Krishna Leela Park) , Konankunte Cross (formerly Anjanapura Cross Road) , Vajrahalli, Thalgattapura and Silk Institute (formerly Anjanapura Township & Anjanapura)
  • Status: Inaugurated on January 14, 2021
Line-2 – Green Line:  Nagasandra – Madavar (formerly BIEC)
  • Length: 3.031 km
  • Type: Elevated
  • Number of Stations: 3
  • Station Names: Manjunathanagar, Chikkabidarakallu (formerly Jindal) and Madavar (formerly BIEC)
  • Status: Became operational on November 7, 2024

Phase 2 Route Map

The embedded map below shows the exact location of all stations and can be zoomed into!

An official PDF route map of Bangalore Metro Phase 2 will be added here when available.

Key for map below: Phase 1 | Phase 2 | Phase 2A | Phase 2B | Phase 3 | Phase 3A

Phase 2 Tenders

Bangalore Metro (BMRCL) Phase 2 tenders can be viewed on the BMRCL’s website. News on these notices, their bidders and contracts are covered in further detail on the news & construction page.

Phase 2’s Contractors

ContractContractor
Detailed Design Consultant (DDC) for Purple Line’s Reach 1 Extension (Byappanahalli to Whitefield) & Green Line’s Reach 4B (Puttenahalli Cross to Anjanapura Township)Mott MacDonald
Detailed Design Consultant (DDC) for Yellow Line (Reach 5)SYSTRA
Detailed Design Consultant (DDC) for Pink Line (Reach 6)AECOM
Detailed Design Consultant (DDC) for depots at Hebbagodi & Kadugodi (Whitefield)Ayesa Ingenieria Y Arguitectura S.A.U.
Purple Line’s Reach 1A: Construction of Baiyappanahalli – Visvesvaraya Ind. Area (viaduct & 6 stations – 8.039 km)ITD Cem India JV
Purple Line’s Reach 1B: Construction of Kundanahalli – Whitefield (viaduct & 7 stations – 7.218 km)ITD Cem India JV
Purple Line’s Reach 2A: Construction of Mysore Road – Pattanagere (viaduct & 4 stations – 3.945 km)IL&FS Engineering Ltd.
Purple Line’s Reach 2B: Construction of Pattanagere – Challegatta (viaduct & 2 stations – 4.869 km)Soma Enterprise Ltd.
Green Line’s Reach 3C: Construction of Hessaraghatta Cross – BIEC (viaduct & 3 stations – 3.031 km)Simplex Infrastructures Ltd.
Green Line’s Reach 4B: Construction of Yelachenahalli – Anjanapura (viaduct & 6 stations – 6.29 km)NCC Ltd.
Yellow Line’s Reach 5 (P1): Construction of Bommasandra to Hosa Road (viaduct & 5 stations – 6.418 km)ITD Cem India JV
Yellow Line’s Reach 5 (P2): Construction of Hosa Road – HSR Layout (viaduct & 6 stations – 6.385 km)ITD Cem India JV
Yellow Line’s Reach 5 (P3): Construction of HSR Layout – RV Road (viaduct & 5 stations – 6.340 km)HCC-URCC JV
Pink Line’s Reach 6 (Elevated): Construction of Gottigere – Swagath Road Cross (viaduct & 5 stations – 7.501 km)GR Infraprojects (contract to Simplex Infrastructures terminated in Feb 2021)
Pink Line’s Reach 6 RT-01: Construction of South Ramp at Dairy Circle – Vellara Junction
(underground tunnels & 3 stations – 3.655 km)
Afcons Infrastructure Ltd.
Pink Line’s Reach 6 RT-02: Construction of Vellara Junction – Shivajianagar
(underground tunnels & 3 stations – 2.755 km)
Larsen & Toubro (L&T)
Pink Line’s Reach 6 RT-03: Construction of Shivajinagar – Tannery Road
(underground tunnels & 2 stations – 2.884 km)
Larsen & Toubro (L&T)
Pink Line’s Reach 6 RT-04: Construction of Tannery Road – North Ramp at Nagawara (underground tunnels & 4 stations – 4.591 km)ITD Cementation
Construction of Purple Line’s Challaghatta Depot structures, roads & drainage worksRITES – PMPL JV
Construction of Purple Line’s Kadugodi Depot structures, roads & drainage worksVascon Engineers Ltd.
Construction of Green Line’s Anjanapura Depot structures, roads & drainage worksBSR Infratech
Construction of Yellow Line’s Hebbagodi Depot structures, roads & drainage worksParnika Commercial & Estates Pvt. Ltd.
Construction of Pink Line’s Kothanur Depot structures, roads & drainage worksISGEC Heavy Engineering Ltd.
150 new intermediate coaches for converting 3-coach trains into 6-coach trains on purple & green lines [ICB No. 2 RS-DM]BEML Ltd.
216 new coaches for purple & green lines (126), and Yellow Line (90) ICB No. 4 RS-DM]CRRC Nanjing Puzhen Co.Ltd.
CBTC signaling system for Reach-5 (Yellow Line) [ICB No. 8 S&T-DM]Siemens
Head Hardened Rails 60E1 – 1080 GradeMitsui & Co. Ltd
Ballastless track of standard gauge in elevated viaduct section and underground section along with ballasted track in depotsTexmaco Rail & Engineering Ltd. (subcontracted to Salasar Adorus Infra in 2021)
Design & Supply of Standard Gauge UIC 60 TurnoutsVossloh Cogifer
Communication Systems for purple & green lines’ four extensions [ICB No.5 S&T (Tele)-DM]Larsen & Toubro Ltd.
Automatic Fare Collection (AFC) System for Phase-II [ICB No. 3 AFC-DM]AGS Transact Technologies Ltd.
Project Management consultancy Services for implementation of AFC SystemErnst and Young LLP
33kV Distribution, 750V DC Third Rail Traction Electrification including Traction Substations, Auxiliary Substations and SCADA System for green and purple lines’ four extensions [ICB No. EP2-CC]Alstom Transport India Ltd.
220/33kV GIS and 66/33kV AIS with 220kV & 66kV Incoming Cabling from Grid Sub-Station for Phase-II [ICB no. EP3-CC]Larsen & Toubro Limited
Escalators for purple & green lines’ four extensions [ICB No. 6 ESCAL – DM]Johnson Lifts Pvt. Ltd.
Elevators for purple & green lines’ four extensions [ICB No. 3 ELEV- DM]OTIS Elevator Company (India) Ltd.
E&M works at Purple Line’s Reach-1A/1B, Green Line’s Reach 3C and Yellow Line’s Reach 5 [BMRCL/Phase-II/E&M-3]Jakson – JSC JV
Elevators for Yellow Line’s Reach-5 and Pink Line’s Reach-6’s elevated stationsJohnson Lifts Pvt. Ltd.
UTO Consultancy for GoA 4 Driverless operationsSYSTRA MVA Consulting (India)
General Consultant for Rolling Stock, Signaling & Platform Screen Doors (Pink Line)SYSTRA – DB Engineering & Consulting – Oriental Consultants Global JV
Pink Line’s Rolling Stock (96 coaches) – Package 5 RS-DMBEML
Pink Line’s signalling & train control and platform screen door/gate systems – Package 10 S&T-DMAlstom Transport India

Click on ‘News & Construction Updates’ below for project news, progress and updates.